Here is schedule of work:

Monday

  • Tacoma - 5 a.m.: Reopen I-5 facilities from Sunday work.
  • DuPont - 7:30 p.m.: Close right lane of northbound I-5 near Mounts Road while crews inspect the rail bridge. This work is part of WSDOT’s Point Defiance Bypass rail project.
  • DuPont - 10 p.m.: Open right lane of northbound I-5 near Mounts Road. Close two left lanes of northbound I-5 at Mounts Road for rail bridge inspection activities.

Tuesday

  • DuPont - 5 a.m.: Reopen northbound I-5 lanes at Mounts Road.
  • DuPont – 7:30 p.m.: Close left lane of southbound I-5 near Mounts Road while crews inspect the rail bridge. This work is part of WSDOT’s Point Defiance Bypass rail project. 
  • Tacoma - 9 p.m.: Close two left lanes of northbound I-5 from South 56th Street to the Puyallup River Bridge.
  • DuPont – 10 p.m.: Close the two left lanes of southbound I-5 at Mounts Road for rail bridge inspection activities. This work is part of WSDOT’s Point Defiance Bypass rail project.
  • Tacoma - 10 p.m.: Reduce northbound I-5 to one lane and detour that lane onto Exit #132, the northbound collector/distributor, and back onto one open northbound I-5 lane. Close the following ramps.  Detours will be provided. 1) South 38th Street on-ramp to SR 7 and I-705;2) southbound I-705 on-ramp to northbound I-5;3) northbound I-5 exit to Portland Avenue.  Motorists are advised to avoid the area if possible and to expect delays.
  • DuPont – 11:30 p.m.: Open left two lanes of southbound I-5. Close the right lane of southbound I-5 and the Mounts Road on-ramp to southbound I-5 for rail bridge inspection activities.  This work is part of WSDOT’s Point Defiance Bypass rail project.

Wednesday

  • Tacoma and DuPont - 5 a.m.: Open all I-5 facilities.
  • Nisqually – 7 p.m.: Close one lane of northbound I-5 for fiber optic cable work.
  • Tacoma - 10 p.m.: Close right lane of northbound I-5 between Portland Avenue and the Puyallup River Bridge and two exits:  1) northbound I-5 exit to State Route 167; and 2) SR 167 on-ramp to northbound I-5.

Thursday
  • 5 a.m.: Open all above facilities.